Under Section 55, where time is NOT of the essence and performance is delayed, the promisee:
ACannot avoid the contract but may claim compensation for the loss caused by delay
BMust accept performance without any remedy
CLoses all remedies
DMay avoid the contract
Answer & Solution
Correct answer: A. Cannot avoid the contract but may claim compensation for the loss caused by delay
When time is not essential, late performance does not make the contract voidable, but the promisee may claim compensation for any loss caused by the delay.
Related questions
Under Section 45, where a promise is made to two or more promisees jointly, the right to cUnder Section 50, performance of a promise may be made in the manner or at the time which:A and B agree A will deliver goods to be paid for on delivery. A need not deliver unless BActual breach of a contract can be committed:Under Section 56, where the promisor alone knew, or with reasonable diligence should have Where a contract becomes impossible or unlawful to perform after it is made, due to an unfAn agreement to do an act impossible in itself (initial impossibility) under Section 56 isUnder Section 55, where time is of the essence of the contract and a party fails to perfor