A kanban system mainly limits the build-up of which item at any point?Read the answer and worked solution →Kanban sets an upper limit on which type of inventory?Read the answer and worked solution →Early two-bin signalling, a kanban forerunner, began in UK factories making which aircraft?Read the answer and worked solution →Toyota first applied kanban logic in its main plant machine shop in which year?Read the answer and worked solution →What does kanban use to control the rate of production?Read the answer and worked solution →How many rules has Toyota formulated for applying kanban?Read the answer and worked solution →Under Toyota's kanban rules, when may an item be made or moved?Read the answer and worked solution →What does a kanban card signal?Read the answer and worked solution →In a three-bin kanban system, where is the inventory control point?Read the answer and worked solution →Which kanban authorizes a workstation to produce a fixed amount?Read the answer and worked solution →Which kanban authorizes moving a full container to the next workstation?Read the answer and worked solution →Electronic kanban replaces physical cards with what?Read the answer and worked solution →Which cycle is Deming particularly recognized for?Read the answer and worked solution →Which kaizen type covers communication of improvements upstream and downstream of a process?Read the answer and worked solution →Which kaizen type has lean spread across the whole organisation, suppliers and customers?Read the answer and worked solution →Which 5S step removes all unnecessary items from a work location?Read the answer and worked solution →Which 5S step puts necessary items in their optimal place for use?Read the answer and worked solution →Which 5S step cleans and inspects the workplace, tools and machinery regularly?Read the answer and worked solution →Which 5S step relies on worker self-discipline?Read the answer and worked solution →In the sort step, where go items that cannot be removed at once?Read the answer and worked solution →5S is identified as a technique that enabled which system?Read the answer and worked solution →In some firms 5S becomes 6S. What is the sixth element?Read the answer and worked solution →Whose 1995 work described 5S in terms of five pillars?Read the answer and worked solution →Who formalized poka-yoke as part of the Toyota Production System?Read the answer and worked solution →Poka-yoke was first called what before being softened?Read the answer and worked solution →A poka-yoke device that checks the prescribed order of steps is which method?Read the answer and worked solution →A mistake becomes a defect, per Shingo, when it does what?Read the answer and worked solution →Who developed Total Productive Maintenance in Japan between 1950 and 1970?Read the answer and worked solution →What is the main objective of TPM?Read the answer and worked solution →How are the three OEE factors combined into one measure?Read the answer and worked solution →

Worked practice questions

A kanban system mainly limits the build-up of which item at any point?

  1. Skilled labour
  2. Machine hours
  3. Customer orders
  4. Excess inventory
Show answer and solution

Correct answer: D. Excess inventory

Limits on items waiting at supply points are set so that excess inventory cannot pile up.

Open this question →

Kanban sets an upper limit on which type of inventory?

  1. Spare parts
  2. Raw material
  3. Finished goods
  4. Work in process
Show answer and solution

Correct answer: D. Work in process

One main benefit is an upper limit on work in process, which avoids overcapacity.

Open this question →

Early two-bin signalling, a kanban forerunner, began in UK factories making which aircraft?

  1. Hurricane
  2. Lancaster
  3. Spitfire
  4. Mosquito
Show answer and solution

Correct answer: C. Spitfire

The empty-box replenishment signal was first developed in UK factories producing Spitfires in the Second World War.

Open this question →

How to practise

  1. Choose a Lean Manufacturing and Kaizen question and try to work out your answer.
  2. Open the question to check the correct answer and read its worked solution.
  3. Continue in the app for bite-sized lessons, explanations and review with Quill. You can start without creating an account.

More Cost and Management Accounting topics