A task needs 240 man-hours. Working 8 hours a day, how many workers finish it in 5 days?

A6
B8
C5
D4
Answer & Solution
Correct answer: A. 6
Each worker gives 8 x 5 = 40 hours, so 240/40 = 6 workers.