If a task requires 20 man-hours, how many hours will a team of 2 workers take?

A10 hours
B20 hours
C40 hours
D15 hours
Answer & Solution
Correct answer: A. 10 hours
Dividing 20 man-hours by 2 available workers gives 10 hours of work.