A man does as much as 3 boys. Two men and 6 boys finish a job in 9 days. How long would 12 boys take?

A6 days
B9 days
C18 days
D12 days
Answer & Solution
Correct answer: B. 9 days
Two men equal 6 boys, so the team equals 12 boys, who therefore also need 9 days.