Twelve men could complete a job in 20 days. After 5 days, 6 men leave. The remaining work takes

A40 days
B25 days
C30 days
D20 days
Answer & Solution
Correct answer: C. 30 days
Work left is 12 x 15 = 180 man-days, and 6 men need 180/6 = 30 days.