Ten women can finish a job in 24 days. After 6 days five women leave. The rest of the job takes
A24 days
B36 days
C30 days
D40 days
Answer & Solution
Correct answer: B. 36 days
After 6 days, 18 days of work for 10 women (180 woman-days) remain, and 5 women need 180/5 = 36 days.
Keep practising Time and Work
Browse all Time and Work questions for RRB NTPC, or explore more Quantitative Aptitude topics.
Related questions
What labor metric denotes the amount of work done by an average worker in a day?How is task time found from man-hours and worker count?If a task requires 20 man-hours, how many hours will a team of 2 workers take?A takes 12 days and B takes 24 days. A leaves 3 days before the work ends. Total time wasA does a job in 16 days, B in 8 days. A works 4 days alone, then B joins. Total time from A alone does a job in 9 days and B alone in 18 days. They earn Rs 900 together. A's share Sita does a job in 30 days. Sita and Tara together do it in 20 days. Tara alone needsA pipe alone fills a tank in 15 minutes; with a second pipe it takes 6 minutes. The second