8 workers finish a job in 6 days at the same pace. How many days would 12 workers need?
A9
B4
C3
D8
Answer & Solution
Correct answer: B. 4
1. Workers and days are inversely proportional, so their product is constant.
2. 8 x 6 = 48 worker-days.
3. 48 / 12 = 4 days; 9 days wrongly treats it as direct proportion.
_Source: Wikipedia, Proportionality (mathematics), Inverse proportionality_
Keep practising Ratio
Browse all Ratio questions for CTET, or explore more Mathematics topics.
Related questions
Which pair of ratios forms a proportion?For what value of x are 4, 6 and x in proportion, meaning 4:6 = 6:x?If 3:5 = x:20, what is x?A speed of 60 km/h is held steady. How far does the car go in 2.5 hours?A mix uses cement : sand = 1:2. If 6 bags of cement are used, how many bags of sand are neMilk and water are mixed 3:2 to make 20 litres. How many litres of water are in it?Rs 900 is shared in the ratio 4:5. What is the bigger share?The ratio of boys to girls in a club is 2:5. There are 14 boys. How many girls are there?