Practice free →
HomeSSC CGLQuantitative AptitudeTime and Work › **Time and Work — formulas used here.** - Work d…

**Time and Work — formulas used here.** - Work done in unit time. If a worker finishes a job in $m$ days, the fraction of work done in one day is $\tfrac{1}{m}$. - Combined work (two workers). A finishes in $X$ days, B in $Y$ days; together they finish in $\tfrac{XY}{X+Y}$ days. - Combined work (three workers). A, B, C take $X$, $Y$, $Z$ days; together they take $\tfrac{XYZ}{XY+YZ+ZX}$ days. - Efficiency–time inverse. If A is $k$ times as efficient as B, A takes $\tfrac{1}{k}$ as long. - Workforce equivalence. $M_1 D_1 T_1 = M_2 D_2 T_2$ for the same work, where $M$ = workers, $D$ = days, $T$ = hours/day. **Question.** A and B together can finish a job in $12$ days. They work together for $4$ days, after which B leaves. A then takes another $18$ days to finish the rest alone. How many days would A alone need to do the entire job?

A$24$
B$27$
C$30$
D$36$
Answer & Solution
Correct answer: B. $27$
Step 1 — work done in $4$ days together: $\tfrac{4}{12} = \tfrac{1}{3}$ of the job. Step 2 — A alone does the remaining $\tfrac{2}{3}$ in $18$ days. So A's daily rate is $\dfrac{2/3}{18} = \dfrac{1}{27}$. Step 3 — at rate $\tfrac{1}{27}$ per day, A alone needs $27$ days to finish the whole job. Distractor check: option A (24) comes from forgetting that the remaining is $\tfrac{2}{3}$ and assuming the rest is half. Option C (30) over-corrects.
Solve this in the app — SSC CGL practice & 24k+ MCQs →
Related questions