Two persons Kuldeep and Agarkar can reap a field in 8 and 12 hours respectively. They work in alternate one-hour shifts, with Kuldeep starting at 9 a.m. When will the reaping finish?
A7:30 p.m.
B4:30 p.m.
C5:30 p.m.
D6:30 p.m.
Answer & Solution
Correct answer: D. 6:30 p.m.
1. Rates: Kuldeep 1/8 per hour, Agarkar 1/12 per hour; a 2-hour cycle does 1/8 + 1/12 = 5/24.
2. After 4 cycles (8 hours, up to 5 p.m.): 4 × 5/24 = 20/24 done, leaving 4/24. Hour 9 (Kuldeep) adds 3/24 → 23/24 at 6 p.m., leaving 1/24.
3. Agarkar does 1/24 in (1/24)÷(1/12) = 0.5 hour, finishing at 6:30 p.m.
_Source: RRB Group D CEN-02/2018 PYQ, Q.52._
Related questions
A and B together complete a work in 12 days. A alone in 18 days. How long does B alone takRohan and Rohit together can finish a job in 10 days, while Rohan alone can do it in 15 daA and B together finish a task in 1.5 days, but A left early and the task took 2 days in aTrij can paint a wall alone in 7.2 days while Madhu takes 10.8 days for the same work. WorIf 200 men can construct a building in 1024 days, how many men are needed to construct theA pipe can fill a tank in 15 hours. Due to a leak at the bottom, it takes 20 hours to fill10 men can finish painting a wall in 8 days. How many more men are needed to finish the saPanu, Jiban and Jalil complete a task alone in 30, 20 and 60 days respectively. Jiban work