Home › Capgemini Hiring › Quantitative Aptitude › Time and Work › Two persons Kuldeep and Agarkar can reap a field…
Two persons Kuldeep and Agarkar can reap a field in 8 and 12 hours respectively. They work in alternate one-hour shifts, with Kuldeep starting at 9 a.m. When will the reaping finish?
A7:30 p.m.
B4:30 p.m.
C5:30 p.m.
D6:30 p.m.
Answer & Solution
Correct answer: D. 6:30 p.m.
1. Rates: Kuldeep 1/8 per hour, Agarkar 1/12 per hour; a 2-hour cycle does 1/8 + 1/12 = 5/24.
2. After 4 cycles (8 hours, up to 5 p.m.): 4 × 5/24 = 20/24 done, leaving 4/24. Hour 9 (Kuldeep) adds 3/24 → 23/24 at 6 p.m., leaving 1/24.
3. Agarkar does 1/24 in (1/24)÷(1/12) = 0.5 hour, finishing at 6:30 p.m.
_Source: RRB Group D CEN-02/2018 PYQ, Q.52._
Related questions
Those two workers, at that combined rate, finish the whole job in:A worker finishing in 5 hours and another in 20 hours together do what share of the job eaConverting two fifths of an hour into minutes gives:In work problems, the parts of the job done by each worker in one hour add up to:Flying into that same 30 mph wind, the same plane's ground speed would be:A plane's ground speed with a tailwind of 30 mph, if the plane itself flies at 150 mph, isOn that drive, Tony's interstate speed was:Tony drives 4 hours in all, 208 miles on the interstate and 40 on country roads, going 15