Plans developed for unique situations and usually replaced after one use are:

ASingle-line plans
BSingle-shift plans
CSingle-stage plans
DSingle-use plans
Answer & Solution
Correct answer: D. Single-use plans
1. Programs, projects and budgets are the three types. 2. They are not reused. 3. They are single-use plans. _Source: OpenStax Principles of Management, Chapter 17, Organizational Planning and Controlling._