A job on Press #1 takes 6 hours. In one hour that press completes:

AOne fifth
BOne sixth
COne third
DOne fourth
Answer & Solution
Correct answer: B. One sixth
1. Six equal hours make the whole job. 2. Each hour is one of those six parts. 3. It completes one sixth. _Source: OpenStax Elementary Algebra, Chapter 8, Solve Uniform Motion and Work Applications._