Worker is paid Rs.20 per day worked and forfeits Rs.3 per idle day. In 60 days he got Rs.280. Idle days:
A15
B20
C40
D30
Answer & Solution
Correct answer: C. 40
1. Let idle days = i. Worked days = 60 − i.
2. 20(60−i) − 3i = 280 → 1200 − 20i − 3i = 280 → 23i = 920.
3. i = 920/23 = 40. So 40 days idle.
_Source: KMAT Karnataka 2023 PYQ Q.33_
Related questions
The equation of the line which contains every point of the form (x, 2x + 3) is:The equation of a line joining (0, 0) and (1, 1) is:The slopes of two perpendicular lines satisfy which relation?The equation of the straight line joining the points (2, 4) and (5, 6) is:If x + y = 10 and x − y = 4, x =If 3x + 2y = 12 and y = 0, x =Slope of y = 4x − 7 is:Solve: 3(x − 2) = 12.