Which is NOT a step in the planning process?

ASetting objectives
BIdentifying alternative courses
CImplementing controls
DSelecting the best alternative
Answer & Solution
Correct answer: C. Implementing controls
1. Planning culminates in selecting the best alternative; control happens afterwards. 2. The standard steps are: set objectives, develop premises, identify and evaluate alternatives, select, formulate sub-plans, implement. 3. Implementing controls is the role of the Controlling function, not Planning. 4. Hence (C) is the function that does NOT belong to Planning. _Source: Maharashtra Balbharati Std XII OCM, Ch 2 "Functions of Management", §2.2 ¶§2.2.1_