Machine A produces a batch in 3 hours; machine B produces the same batch in 2 hours. How long do they take together?
A5 hours
B2.5 hours
C1.5 hours
D1.2 hours
Answer & Solution
Correct answer: D. 1.2 hours
Rates add when machines work in parallel: $1/3 + 1/2 = 1/x$. Common denominator 6: $2/6 + 3/6 = 5/6$, so $1/x = 5/6$ and $x = 6/5 = 1.2$ hours, that is 1 hour 12 minutes. Option A wrongly adds the individual times; option B halves that sum.
Related questions
GMAT DS questions should be paced at:The sum of 5 consecutive integers is always divisible by:If x² = 36, what can we conclude about x?A GMAT PS question asks: 'What is x if 3x + 5 = 23?' Options: 4, 5, 6, 7. The fastest apprOn a percentage question with abstract values, the recommended smart-number to assume is:Is 1,287 divisible by 3?In a GMAT DS question, what is the FIRST step?In GMAT DS, answer choice (A) is selected when: