What method was developed to reduce cost overruns?

ALean startup principles
BAffordable loss principle
CBalanced scorecard approach
DReference class forecasting
Answer & Solution
Correct answer: D. Reference class forecasting
Reference class forecasting was developed to lower the risk of cost overruns and revenue shortfalls in business plans.