A works twice as fast as B. Together they finish in 12 days. A alone takes
A6 days
B18 days
C36 days
D24 days
Answer & Solution
Correct answer: B. 18 days
If B does r per day then A does 2r, so 3r = 1/12 and r = 1/36; A alone needs 18 days.
Keep practising Ratio and Proportion, Indices and Logarithms
Browse all Ratio and Proportion, Indices and Logarithms questions for CA Foundation, or explore more Quantitative Aptitude topics.
Related questions
If log base x of 64 equals 3, then x equalsThe value of log base 5 of 125 plus log base 2 of 8 isFor positive a and b (not 1), (log base a of b) x (log base b of a) equalsLog of a product xy equalsIf log10 of an integer is 3.78, how many digits does it have?Who published the first set of base-10 logarithms in 1617?Who introduced logarithms in 1614?The base of the natural logarithm is approximately