A promisee accepts late performance under a voidable contract. When can he still claim compensation?

AIf he gave notice then
BIn every single case
CIn no case whatever
DOnly after one year
Answer & Solution
Correct answer: A. If he gave notice then
Section 55 bars compensation for the delay unless notice of intention to claim it is given when the late performance is accepted.