In value engineering, value is the ratio of what?

  1. Function to cost
  2. Cost to price
  3. Output to input
  4. Profit to sales
Show answer and solution

Correct answer: A. Function to cost

Value can be raised by improving function or by cutting cost.

Open this question →

Value engineering began during World War II at which firm?

  1. Boeing Company
  2. General Electric
  3. Ford Motor Co.
  4. Toyota Motor
Show answer and solution

Correct answer: B. General Electric

Shortages of labour and materials led General Electric staff to find substitutes, which became value analysis.

Open this question →

A primary tenet of value engineering is that basic what be preserved?

  1. Costs
  2. Functions
  3. Suppliers
  4. Prices
Show answer and solution

Correct answer: B. Functions

Savings must not reduce the product's basic functions.

Open this question →

How to practise

  1. Choose a Introduction to Strategic Cost Management question and try to work out your answer.
  2. Open the question to check the correct answer and read its worked solution.
  3. Continue in the app for bite-sized lessons, explanations and review with Quill. You can start without creating an account.

More Cost and Management Accounting topics