A firm estimates overhead of 400,000 and direct labour of 200,000. Applied overhead per labour dollar is:

A4.00
B1.50
C2.00
D0.50
Answer & Solution
Correct answer: C. 2.00
1. Divide estimated overhead by the estimated activity base. 2. 400,000 divided by 200,000 gives two. 3. That is 2.00 of overhead for each 1.00 of direct labour. _Source: OpenStax Principles of Managerial Accounting, Chapter 4, Job Order Costing._