A contractor builds one custom deck designed for a single client's garden. Costs are best traced using:
AJob order costing
BJoint order costing
CJournal entry costing
DJobbing rate costing
Answer & Solution
Correct answer: A. Job order costing
1. The work is unique and made to that customer's order.
2. Every material and labour cost can be tied to that one deck.
3. Tracing costs to an individual job is job order costing.
_Source: OpenStax Principles of Managerial Accounting, Chapter 4, Job Order Costing._
Keep practising Job Order Costing
Browse all Job Order Costing questions for CIMA Management Level, or explore more Accounting topics.