Anyone involved in a project, or affected by what it delivers, counts as a:

AStakeholder
BShareholder
CContractor
DCompetitor
Answer & Solution
Correct answer: A. Stakeholder
1. Involvement or impact is enough. 2. It is deliberately broad. 3. That person is a stakeholder. _Source: OpenStax Foundations of Information Systems, Chapter 9, Information Systems Project Management._