The plant is running and the manager now watches scrap rates, costs and the day's schedule. This stage is:

AProduction control
BProduction design
CProduction launch
DProduction audit
Answer & Solution
Correct answer: A. Production control
1. Planning has already happened. 2. The factory is now running. 3. This is production control. _Source: OpenStax Introduction to Business, Chapter 10, Achieving World-Class Operations Management._