A project with a negative net present value should be:
ARejected
BRepeated
CExtended
DRewarded
Answer & Solution
Correct answer: A. Rejected
1. A negative net present value means the project destroys value.
2. Projects with a negative NPV should be rejected.
3. Managers should reject any project with a negative NPV.
4. So the decision is to reject.
_Source: OpenStax Principles of Finance (CC BY 4.0), Ch 16 'How Companies Think about Investing', sections 16.1-16.5_
Keep practising Capital Budgeting
Browse all Capital Budgeting questions for US CMA Part 2, or explore more Finance topics.
Related questions
Find the crossover rateWhich figure is higherSpot the false ruleLeave the strength standingAccept it or reject itThe discounted payback period improves on plain payback by first doing what to the cash flA machine costs $16,000 and the added cash inflow recovers that cost over four years. PaybThe NPV method and the profitability index method will always agree on: