A project with a positive net present value should be:

ADuplicated
BAccepted
CCancelled
DPostponed
Answer & Solution
Correct answer: B. Accepted
1. Net present value measures the value a project creates. 2. A positive figure means the project adds value. 3. Projects with a positive NPV should be accepted. 4. So the decision is to accept. _Source: OpenStax Principles of Finance (CC BY 4.0), Ch 16 'How Companies Think about Investing', sections 16.1-16.5_