One unit needs 8.6 pounds at $6.00 a pound, 5 hours at $10.00 an hour and 1 hour of factory overhead at $12.00 an hour. What is the standard cost per unit?
A$101.60
B$113.00
C$113.60
D$125.60
Answer & Solution
Correct answer: C. $113.60
1. Direct materials: 8.6 pounds times $6.00 gives $51.60 per unit.
2. Direct labour: 5 hours times $10.00 gives $50.00 per unit.
3. Factory overhead: 1 hour times $12.00 gives $12.00 per unit.
4. Adding the three product costs gives $51.60 plus $50.00 plus $12.00, which is $113.60.
5. $101.60 leaves out the factory overhead element entirely.
_Source: Jonick, Principles of Managerial Accounting (UNG Press, CC BY-SA 4.0), section 8.1 Introduction_
Related questions
Gross profit is $86,830, selling expenses are $18,300 and administrative expenses are $9,1Gross profit at standard is $86,400 and the net variance from standard cost is $430 favourNormal capacity is 10,000 standard hours, 11,000 standard hours apply to the units produceNormal capacity is 10,000 standard hours, 8,000 standard hours apply to the units producedActual variable factory overhead is $39,500 and budgeted variable factory overhead for theThe variable factory overhead rate is $5 per direct labour hour and 8,000 units are producBudgeted factory overhead at normal capacity is $120,000 and normal capacity is 10,000 dirA direct labour time variance of $1,000 unfavourable sits alongside a rate variance of $2,