Golf carts absorb $117,000 of fabrication, $64,000 of assembly, $46,000 of setup and $49,000 of inspection overhead, and 500 golf carts are budgeted. What is the overhead per golf cart?
A$430 per unit
B$552 per unit
C$505 per unit
D$620 per unit
Answer & Solution
Correct answer: B. $552 per unit
1. Add the four activity costs charged to golf carts: $117,000 plus $64,000 plus $46,000 plus $49,000.
2. That total is $276,000 of factory overhead for the whole golf cart line.
3. Divide by the 500 golf carts budgeted for the year.
4. $276,000 divided by 500 units gives $552 per unit.
5. $430 per unit is the go kart figure, built from $301,000 over 700 units.
6. Dividing by the wrong output volume is the usual slip here, since the two products have different unit counts.
_Source: Jonick, Principles of Managerial Accounting (UNG Press, CC BY-SA 4.0), section 4.6 Activity-Based Costing for a Manufacturing Business to Estimate Factory Overhead_
Related questions
Moving to activity-based costing tends to change the per-unit cost of low-volume products One stated disadvantage of activity-based costing is that the method is:When the entire finished goods inventory is sold, net income under the two methods is:Fixed overhead is $12,000 and 10,000 units are made. Under absorption costing each unit caWhy is activity-based costing described as a more accurate way of allocating overhead?In the five stages of activity-based costing, activity rates are calculated for each:Absorption costing applies all direct costs, fixed overhead and variable overhead to the:Under variable costing, fixed overhead costs are treated in which way?