Which budget must be completed before the production budget can be prepared?
AThe factory overhead cost budget
BThe direct labor cost budget
CThe sales budget for the year
DThe cash budget for the year
Answer & Solution
Correct answer: C. The sales budget for the year
1. The sales budget is prepared first, by estimating the number of units that will be sold.
2. The production budget begins with that estimated number of units to be sold.
3. Desired ending inventory is added and beginning inventory is deducted to get units to produce.
4. The labor and overhead budgets come later in the chain, so neither can precede production.
_Source: Jonick, Principles of Managerial Accounting (UNG Press, CC BY-SA 4.0), section 7.6 Sales Budget_
Related questions
How should budget figures be understood once the period they cover has ended?A capital expenditures budget for 2021 lists cutting machinery $18,000, assembly machineryWhat does a capital expenditure budget list?January estimated cash receipts are $118,000, including $50,000 from issuing stock, and esMarch cash payments are $18,600 for cash purchases, $26,040 for March purchases on accountA company pays 30% of purchases in cash and 60% of purchases on account in the month of puIn March a company collects $24,800 of cash sales, $39,680 from March sales on account, $3January sales are $68,000, of which 20% are for cash and the rest on account, and 40% of s