A budget prepared for a single, standard level of activity is a
Afixed budget
Bflexible budget
Ccash budget
Dzero based budget
Answer & Solution
Correct answer: A. fixed budget
1. Budgets differ by how they treat the level of activity.
2. A fixed budget is prepared on the basis of a standard or fixed level of activity.
3. It is not adjusted when the actual level turns out different.
4. A flexible budget, by contrast, recognises several activity levels.
_Source: ICAI Cost and Management Accounting Ch15 'Budgets and Budgetary Control', section 15.7_
Related questions
Budgetary control compares actual results againstUnder a fixed budget, comparing actual cost at a different activity level is misleading beA cash budget is primarily concerned withZero based budgeting differs from traditional budgeting because itThe budget that consolidates all functional budgets into a single statement is theA forecast of the output planned for the budget period is theA flexible budget is more useful for control because it