Complete the material price variance

Exercise and reference answers

Missing parts
  1. Answer
    Quantity
    Choices
    1. Quantity
    2. Value
    3. Rate
  2. Answer
    standard
    Choices
    1. budgeted
    2. standard
    3. revised
  3. Answer
    actual
    Choices
    1. standard
    2. average
    3. actual
Complete the statement
Material Price Variance = Actual {0} multiplied by the difference between {1} price and {2} price.
Instructions
Tap a term into each blank to finish the variance formula.

Explanation

_Source: ICAI CA Inter Cost and Management Accounting, Ch13 'Standard Costing', 13.7.1_