Per §5.4.5, in the Kelly Ball test the minimum depth of concrete needed for a valid result is:
A{'text': '5 cm', 'label': 'A'}
B{'text': '10 cm', 'label': 'B'}
C{'text': '20 cm', 'label': 'C'}
D{'text': '50 cm', 'label': 'D'}
Answer & Solution
Correct answer: C. {'text': '20 cm', 'label': 'C'}
1. §5.4.5: 'The minimum depth of concrete must be a minimum of 20 cms and minimum distance from the centre of the ball to nearest edge of concrete has to be minimum 23 cms.'
2. The procedure (level surface, place tester, lower the ball gradually, read to nearest 6 mm) takes only ~15 seconds per measurement.
_Source: IGNOU ET-522 Block-2 Unit-5 Workability & Fresh Concrete-I, §5.4.5, p. 13_
Related questions
Per §5.6, remedial measures listed by the source for excessive bleeding include all the foPer §5.6, harmful effects of bleeding listed in the source include all of the following EXPer §5.6, 'laitance' formed at the surface of concrete by bleeding is:Per §5.6, 'bleeding' of concrete is best defined as:Per §5.5, segregation in fresh concrete refers to:Per §5.4.6 (Vee-Bee Consistometer Test), the test is described as most suitable for assessPer §5.4.5 (Kelly Ball Test), the metal hemispherical indenter used has a diameter of abouPer §5.4.4, in the standard Flow Test the flow table is dropped through 12.5 mm at the rat