If 12 men can do a job in 8 days, in how many days will 16 men do the same job?
A4
B6
C8
D12
Answer & Solution
Correct answer: B. 6
1. Total work = 12 × 8 = 96 man-days.
2. With 16 men: time = 96/16.
3. = 6 days.
_Source: KMAT Karnataka 2022 PYQ Q.79_
Related questions
Those two workers, at that combined rate, finish the whole job in:A worker finishing in 5 hours and another in 20 hours together do what share of the job eaConverting two fifths of an hour into minutes gives:In work problems, the parts of the job done by each worker in one hour add up to:Flying into that same 30 mph wind, the same plane's ground speed would be:A plane's ground speed with a tailwind of 30 mph, if the plane itself flies at 150 mph, isOn that drive, Tony's interstate speed was:Tony drives 4 hours in all, 208 miles on the interstate and 40 on country roads, going 15