Practice free →
Home › If 8 men complete a job in 12 days, then 4 men w…

If 8 men complete a job in 12 days, then 4 men working at twice the speed will finish it in:

A6 days
B12 days
C24 days
D48 days
Answer & Solution
Correct answer: B. 12 days
1. Total work = 8 men × 12 days = 96 man-days at original speed. 2. 4 men at twice the speed = 4 × 2 = 8 effective men. 3. Time = 96 / 8 = 12 days. _Source: KMAT Karnataka 2022 PYQ Q.60_
Solve this in the app — Practice practice & 24k+ MCQs →