Forecast differs from budget because forecast is:
AA target
BA probable estimate
CAlways accurate
DA legal document
Answer & Solution
Correct answer: B. A probable estimate
1. Forecast is an assessment of probable future events.
2. A budget is a commitment or target the management seeks to attain.
3. Forecasts allow flexibility; budgets do not.
4. Hence forecast is a probable estimate.
_Source: ICAI BoS Inter Paper 3, Ch 15 "Budget", §15.1 ¶6_
Related questions
Activity-based budgeting allocates cost to:Limitations of budgeting do NOT include:Programme budgeting allocates resources to:ZBB rejects:Master budget includes:Cash budget receipts: opening cash 10,000; sales receipts 60,000; payments 50,000. ClosingIf actual sales are 1,05,000 units versus budget of 1,00,000 units at standard contributioSales budget for the year is 1,20,000 units split equally across four quarters. With seaso