Forecast differs from budget because forecast is:

AA target
BA probable estimate
CAlways accurate
DA legal document
Answer & Solution
Correct answer: B. A probable estimate
1. Forecast is an assessment of probable future events. 2. A budget is a commitment or target the management seeks to attain. 3. Forecasts allow flexibility; budgets do not. 4. Hence forecast is a probable estimate. _Source: ICAI BoS Inter Paper 3, Ch 15 "Budget", §15.1 ¶6_