Blanket overhead rate is single rate for:
AEach product
BEach department
CWhole factory
DEach machine
Answer & Solution
Correct answer: C. Whole factory
1. Blanket rate is computed once for the entire factory using total overhead divided by total activity.
2. It ignores variation across departments.
3. Departmental rates are more accurate when departments differ materially in overhead intensity.
4. Hence blanket overhead rate applies to the whole factory.
_Source: ICAI BoS Inter Paper 3, Ch 4 "Overheads", §4.5.3 ¶1_
Related questions
Activity-based costing improves on traditional absorption by:Stores keeping cost is best apportioned to producing departments using:Idle capacity cost should be:Predetermined overhead rate is used because actual rate becomes available only:Departmentalisation of overheads aids:Selling overhead is best apportioned on the basis of:Reciprocal services between two service departments are best handled by:Recovery of overheads on percentage of direct wages basis is calculated as: