A can do a piece of work in 12 days and B in 18 days. They begin together, but A leaves 2 days before the work is completed. In how many days is the work finished?
A43/5 days
B7 days
C8 days
D42/5 days
Answer & Solution
Correct answer: D. 42/5 days
1. Let total time be T. B works all T days; A works (T − 2) days.
2. (T − 2)/12 + T/18 = 1. Multiply by 36: 3(T − 2) + 2T = 36.
3. 3T − 6 + 2T = 36 ⇒ 5T = 42 ⇒ T = **42/5 days** (8.4 days).
_Source: IBPS RRB Officer Scale I Prelims PYQ (Examrace), Q.69_
Related questions
A and B together complete a work in 12 days. A alone in 18 days. How long does B alone takRohan and Rohit together can finish a job in 10 days, while Rohan alone can do it in 15 daA and B together finish a task in 1.5 days, but A left early and the task took 2 days in aTrij can paint a wall alone in 7.2 days while Madhu takes 10.8 days for the same work. WorIf 200 men can construct a building in 1024 days, how many men are needed to construct theTwo persons Kuldeep and Agarkar can reap a field in 8 and 12 hours respectively. They workA pipe can fill a tank in 15 hours. Due to a leak at the bottom, it takes 20 hours to fill10 men can finish painting a wall in 8 days. How many more men are needed to finish the sa