12 workers finish a job in 8 days. In how many days can 16 workers finish the same job?
A4 days
B5 days
C7 days
D6 days
Answer & Solution
Correct answer: D. 6 days
Total work = 12 * 8 = 96 worker-days. Required days = 96 / 16 = 6 days.