A can do a piece of work in 12 days and B in 18 days. Together they finish it in
A8.4 days
B9.0 days
C6.5 days
D7.2 days
Answer & Solution
Correct answer: D. 7.2 days
Combined rate = 1/12 + 1/18 = 3/36 + 2/36 = 5/36. Time = 36/5 = 7.2 days.
Related questions
In a right triangle with legs 5 cm and 12 cm, the hypotenuse isThe volume of a cube of side 4 cm isThe perimeter of a square is 36 cm. Its area isThe area of a circle with radius 7 cm is (use pi = 22/7)The smallest number divisible by both 12 and 18 isThe sum of three consecutive natural numbers is 72. The middle number isIf x + y = 12 and x - y = 4, then xy equalsA sum of money doubles itself in 8 years at simple interest. The rate per annum is