Match each deviation analysis technique with its managerial principle:
A1-A, 2-B, 3-C
B1-B, 2-A, 3-C
C1-C, 2-B, 3-A
D1-A, 2-C, 3-B
Answer & Solution
Correct answer: A. 1-A, 2-B, 3-C
MBE escalates only major variances. CPC focuses on key result areas. Corrective action fixes root causes.
Keep practising Controlling
Browse all Controlling questions for CBSE Class 12 (Commerce), or explore more Business Studies topics.
Related questions
Match each traditional or modern controlling technique with its tool:Match each dimension of the Planning-Controlling relationship:Match each step in the controlling process with its sequence:The concept of organizational control is implicit in whose bureaucratic theory?Operational control regulates what aspect of an organisation?Which feature is an essential part of any closed-loop system?A home thermostat is a standard example of which kind of control system?A street light switched on by a timer, regardless of darkness, is an example of what?