6 workers at equal fixed rates need 5 days at 4h/day. Same job: days for 4 workers at 6h/day?

A5 days
B7.5 days
C3⅓ days
D10 days
Answer & Solution
Correct answer: A. 5 days
The work needs 6 × 5 × 4 = 120 worker-hours; four workers provide 24 hours of labour daily, so five days suffice.