What is the renewable energy capacity target set for Coal Ministry PSUs by FY 2029-30?
A14.4 GW
B7.0 GW
C5.0 GW
D78.235 GW
Answer & Solution
Correct answer: A. 14.4 GW
Ministry of Coal has targeted 14.4 GW renewable energy capacity by 2029-30: NLCIL 7.0 GW, CIL 5.0 GW and SCCL 2.4 GW.
Till December 2024, 1,796.5 MW had been commissioned (NLCIL 1,431 MW, SCCL 245.5 MW, CIL 120 MW). (
Source: AR 2024-25 Ch 4 section 1.2.)
Keep practising CPSU Diversification — Gasification JVs, Renewables, CBM, Critical Minerals
Browse all CPSU Diversification — Gasification JVs, Renewables, CBM, Critical Minerals questions for Coal India MT, or explore more Energy topics.
Related questions
By the date of the AR 2024-25 report, how much renewable-energy capacity had CIL commissioHow many Pump Storage Plant projects are planned in the first phase by CIL and NLCIL?Which graphite block has CIL already acquired as part of its critical minerals strategy?Under PM Surya Ghar Muft Bijli Yojana, how much solar capacity is planned to be installed