What is the renewable energy capacity target set for Coal Ministry PSUs by FY 2029-30?

A14.4 GW
B7.0 GW
C5.0 GW
D78.235 GW
Answer & Solution
Correct answer: A. 14.4 GW
Ministry of Coal has targeted 14.4 GW renewable energy capacity by 2029-30: NLCIL 7.0 GW, CIL 5.0 GW and SCCL 2.4 GW. Till December 2024, 1,796.5 MW had been commissioned (NLCIL 1,431 MW, SCCL 245.5 MW, CIL 120 MW). ( Source: AR 2024-25 Ch 4 section 1.2.)