A plant has fixed costs of Rs 6,000 and makes 30 units with variable cost of Rs 150 each. What is the full cost per unit?
ARs 200
BRs 330
CRs 350
DRs 180
Answer & Solution
Correct answer: C. Rs 350
Fixed cost per unit is 6,000 / 30 = Rs 200, so full cost is 150 + 200 = Rs 350.
Keep practising Standard Costing and Variance Analysis
Browse all Standard Costing and Variance Analysis questions for CA Final, or explore more Cost and Management Accounting topics.
Related questions
Management accounting information is computed by reference to whose needs?Variance analysis compares actual and budgeted cost of which inputs?What happens in management by exception when a deviation from the norm is insignificant?In passive management by exception, when does the manager step in?An adverse variance exists when budget versus actual leads to what effect on profit?Under standard costing, where are fixed costs of unsold goods made in a period carried forVariance analysis is a tool of budgetary control and of what other function?Besides costs, variance analysis can also be carried out for which other item?