Std variable overhead Rs 4 per hour. Std hours 500, actual hours 520. Efficiency variance in Rs?

A80 favourable
B80 adverse
C2,000 adverse
D20 adverse
Answer & Solution
Correct answer: B. 80 adverse
Twenty hours above standard at Rs 4 per hour gives Rs 80, adverse because more hours were used.