In project risk work, Pareto analysis helps focus on which risks?

ALongest-standing risks
BHighest-impact risks
CNewest risks logged
DCheapest risks to fix
Answer & Solution
Correct answer: B. Highest-impact risks
It directs management to the risks with the most impact on the project.