How should costs untraceable to any activity be treated in ABC?

ALoaded on top product
BKept as unallocated
CSpread by sales value
DSpread by headcount
Answer & Solution
Correct answer: B. Kept as unallocated
ABC exists to inform management, so no cost should be assigned in an arbitrary manner.