Before the project ends, how is the contractor paid?

AOn a cost reimbursement basis
BAs a single fixed lump sum
CBy milestone bonuses alone
DAt a fixed market price
Answer & Solution
Correct answer: A. On a cost reimbursement basis
During the project the contractor is reimbursed its costs, and the gain or pain is settled only at the end.