Actual cost is below target cost. What does the contractor get?

AA fine equal to the saving
BOnly its original fee
CA pre-agreed share of gain
DThe full saving alone
Answer & Solution
Correct answer: C. A pre-agreed share of gain
The contractor is rewarded with a share of the saving at a percentage agreed in advance.