In target value design for construction, when is the target cost developed?

AAt project handover
BFrom the very beginning
CAfter tendering ends
DAt the final audit
Answer & Solution
Correct answer: B. From the very beginning
The team fixes a target cost at the outset and treats it as a design parameter like capacity.