Target costing is described as which approach to cost management?
AReactive variance review
BProactive cost planning
CHistorical cost recording
DYear-end cost audit
Answer & Solution
Correct answer: B. Proactive cost planning
Costs are planned and managed from the design stage, before production starts.
Keep practising Cost Volume Profit Analysis and Pricing Decisions
Browse all Cost Volume Profit Analysis and Pricing Decisions questions for CA Final, or explore more Cost and Management Accounting topics.
Related questions
Fixed costs are Rs 20,000 and variable cost is Rs 6 a unit. Total cost at 4,000 units?Margin of safety shows how far sales can fall before what?Which action lowers the break-even point?A firm needs 200 tables to break even but sells fewer. How is it operating?Target costing was developed independently in the USA and which country?Market-driven target costing identifies a product's what?Which technique is most critical in reaching a target cost?A product will sell at Rs 500 and needs a 20% margin on price. What is the target cost?