A line runs 85 percent of planned time, at 90 percent of ideal speed, with no rejects. OEE?

A75.0%
B76.5%
C87.5%
D79.5%
Answer & Solution
Correct answer: B. 76.5%
OEE = 0.85 x 0.90 x 1.00 = 0.765, or 76.5 percent.